P, Q and R working alone can complete a piece of work in 11 days, 20 days and 55 days respectively. If P is helped by Q and R on alternate days, in how many days can the work be completed?
- 18 days✓
- 224 days
- 39 days
- 431 days
Correct answer
8 days