Mathematics · Work and Time
P, Q, and R can individually complete a work in 10, 12, and 15 days respectively. They start working together, but P leaves after 2 days and Q leaves 3 days before the completion of the work. In how many days was the work completed?
- 16
- 25
- 37✓
- 48
Correct answer
7