P, Q, and R can complete a project in 8, 6, and 12 days respectively. The project is started with P and Q working on Day 1, Q and R working on Day 2, R and P working on Day 3, and this alternate pattern continues. In how many days will the project be completed?
- 1227 days
- 2297 days
- 3277 days✓
- 4347 days
Correct answer
277 days