Mathematics · Time and Work
P completes 13 part of a work in 15 days and Q completes the remaining work in 45 days. In how many days can they together finish the entire work?
- 125 days
- 221 days
- 330 days
- 427 days✓
Correct answer
27 days
Download Single Question PDF