P can complete a project in 12 days, and Q can complete the same project in 18 days. They work together for 6 days, after which the remaining work is completed by R in 3 more days. If the total payment for the entire project is Rs. 3600, what are the daily wages of P, Q, and R respectively (in Rs)?
- 1200, 150, 250
- 2300, 200, 200✓
- 3300, 200, 150
- 4250, 200, 300
Correct answer
300, 200, 200