Mathematics · Time and Work
P and Q working alone can complete a work in 5 days and 15 days respectively. They work on alternate days one at a time. If P works on the first day, in how many days will the whole work be completed?
- 18
- 27.5
- 37✓
- 46
Correct answer
7