P and Q together can complete a work in 30 days. They started the work together but after 20 days P left the work. If the remaining work is completed by Q in 50 more days, then P alone can complete the entire work in how many days?
- 1150 days
- 233.33 days
- 3170 days
- 437.5 days✓
Correct answer
37.5 days