P and Q agree to complete a project for ₹450. P can complete it alone in 20 days and Q in 40 days. With the assistance of R, they complete the entire work together in 8 days. What is R's share of the payment?
- 1₹40
- 2₹150
- 3₹180✓
- 4₹60
Correct answer
₹180