On 1 October 20X4, Constructo Co entered into a fixed-price contract to build a bridge for a customer for $10 million. Constructo Co satisfies the performance obligation over time and measures progress using the input method (costs incurred to date as a proportion of total expected costs). At the year-end of 31 December 20X4, the following details are available: * Costs incurred to date: $2.4 million * Estimated costs to complete: $5.6 million * Amounts billed to the customer: $2.8 million * Cash received from the customer: $2.0 million What is the value of the contract asset or liability to be recognized in Constructo Co's statement of financial position as at 31 December 20X4?
- 1$400,000 Contract Liability
- 2$1,000,000 Contract Asset
- 3$200,000 Contract Asset✓
- 4$200,000 Contract Liability
Correct answer
$200,000 Contract Asset
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Financial Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Financial Accounting