Accounting · Provisions and Contingencies
On 1 January 20X4, Star Co completed the construction of a power plant that has an estimated useful life of 20 years. Star Co immediately started to use the power plant. Star Co is required, by law, to restore the site on which the plant is built at the end of its useful life. At 1 January 20X4 the estimated cost of dismantling the plant and restoring the site after 20 years was $5 million. The cost of capital of Star Co is estimated at 8.5%. The present value of $1 after 20 years is 0.196. What interest expense should Star Co recognise for the year ended 31 December 20X5 in relation to the power plant?
- 1$425,000
- 2$83,300
- 3$90,381✓
- 4$49,000
Correct answer
$90,381
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Provisions and Contingencies?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Provisions and Contingencies