Mathematics · Time and Work
Neelakshi started a work and worked alone for 15 days, completing 50% of it, and then left. Kanupriya completed the remaining work alone in 20 days. Find the time taken by Neelakshi and Kanupriya working together to complete 87.5% of the same work.
- 112 days
- 213 days
- 315 days✓
- 414 days
Correct answer
15 days