Mathematics · Time and Work
Mohi and Suniti working separately can do a work in 12 and 15 days, respectively. Mohi starts the work and they work on alternate days. In how many days will the work be completed?
- 11214 days
- 21314 days✓
- 3144 days
- 4164 days
Correct answer
1314 days