Mohan can complete a piece of work in 24 days. He worked for 6 days and left the work. Thereafter, Sohan finished the remaining work in 21 days. In how many days can Mohan and Sohan together complete it?
- 1121013 days
- 2121113 days
- 312913 days
- 4121213 days✓
Correct answer
121213 days