Mathematics · Time and Work
Mohan and Ramesh can together complete a work in 15 days. Mohan is 50% more efficient than Ramesh. The time taken by Mohan alone to complete the work is:
- 120 days
- 232 days
- 325 days✓
- 422.5 days
Correct answer
25 days