Mathematics · Flexed Budgets and Variance Analysis
MB Co uses flexed budgets. The fixed budget for last month was based on 100% activity and showed variable direct costs of $100,000. Last month's actual direct costs were $93,600, which resulted in a $2,400 Adverse variance when compared with the flexed budget. What was the actual activity as a percentage of the fixed budget last month?
- 197.5%
- 296.0%✓
- 393.6%
- 491.2%
Correct answer
96.0%
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Flexed Budgets and Variance Analysis?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Flexed Budgets and Variance Analysis