Match the various overhead charges with their approximate percentage of estimated cost in building estimation: A. Tools and plants - I. 10% to 15% B. Contingency - II. 1% to 1.5% C. Supervision charges - III. 1.5% to 2% D. Work-charged establishment - IV. 3% to 5%
- 1A-IV, B-I, C-II, D-III
- 2A-II, B-IV, C-III, D-I
- 3A-II, B-III, C-IV, D-I
- 4A-II, B-IV, C-I, D-III✓
Correct answer
A-II, B-IV, C-I, D-III