Match the systems/techniques (List I) with their primary usage (List II): List I: A. PERT B. DFD C. CPM D. LibQual List II: I. Used for the physical and logical descriptions of a system II. Generally uses two pairs of time/cost estimates: a normal schedule and a crash schedule III. Involves concepts like Event, Activity, Dummy activity, and Merge event IV. Based on service quality evaluation by users
- 1A - III, B - I, C - II, D - IV✓
- 2A - I, B - II, C - III, D - IV
- 3A - II, B - III, C - IV, D - I
- 4A - III, B - IV, C - I, D - II
Correct answer
A - III, B - I, C - II, D - IV
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Library Management and Systems?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Science · Library Management and Systems