Match the following nomenclature with their correct definitions in civil engineering estimation: Nomenclature: (i) Work Value (ii) Actual cost (iii) Administrative approval Definition: (p) Real expenditure incurred, which includes incidental, establishment, and travel charges (q) Estimate for contingencies, work establishment, tools & plants (r) Formal acceptance or authorization from the governing body for incurring an expenditure on work
- 1i - p; ii - q; iii - r
- 2i - q; ii - r; iii - p
- 3i - p; ii - r; iii - q
- 4i - q; ii - p; iii - r✓
Correct answer
i - q; ii - p; iii - r
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimating and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimating and Costing