Mathematics · Time and Work
M, R, S and B can complete a work individually in 5 days, 6 days, 15 days and 10 days respectively. If only one person works on any given day and the four workers work alternately starting with R, followed by B, S and M in that order until the work is completed, in how many days will the work be finished?
- 19 34 days
- 26 17 days
- 38 16 days
- 47 23 days✓
Correct answer
7 23 days