John can complete a piece of work in 6 days working 8 hours each day, and Manu can complete it in 3 days working 4 hours each day. How long will they take to complete it if they work together 93/5 hours a day?
- 14 days
- 21 day✓
- 33 days
- 42 days
Correct answer
1 day