Mathematics · Time and Work
Individually, A, B, and C can complete a task in 8, 10, and 15 days, respectively. A and B begin the job, but after 2 days of working, A leaves. After that, C continues working alongside B. How many total days will it take to complete the entire work?
- 15310 days✓
- 21050 days
- 32310 days
- 4310 days
Correct answer
5310 days