In which type of construction contract does the total amount a contractor receives depend on the quantities of various descriptions of work actually executed?
- 1Lumpsum contract
- 2Cost plus flexible percentage contract
- 3Cost plus fixed percentage contract
- 4Item rate contract✓
Correct answer
Item rate contract