Computer · Estimation and Costing
In which method is the estimate prepared by considering the external dimensions of the building at the plinth level?
- 1Cube rate estimate method
- 2Revised estimate method
- 3Plinth area estimate method✓
- 4Supplementary estimate method
Correct answer
Plinth area estimate method