Computer Science · Software Engineering
In unit testing of a model, it is found that for a set of test data, at the maximum 90% of the code alone was tested with a probability of success of 0.9. What is the maximum possible reliability of the model?
- 1greater than 0.9
- 2equal to 0.9
- 3at most 0.81✓
- 4at least 10.81
Correct answer
at most 0.81