General Studies · Production Planning and Control
In the scope of production planning and control functions, pre-planning activity typically concludes with the outputs delivered to which phase or department?
- 1The raw material procurement site
- 2The operations scheduling and active manufacturing routing department✓
- 3The end consumer
- 4Dispatching the finished product
Correct answer
The operations scheduling and active manufacturing routing department
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Production Planning and Control?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Production Planning and Control