General Studies · Network Analysis PERT and CPM
In the Program Evaluation and Review Technique (PERT), activity durations are assumed to follow a beta distribution because:
- 1It is a unimodal distribution bounded by optimistic and pessimistic estimates, flexible enough to model time uncertainties✓
- 2It has a finite non-negative error only
- 3It is always strictly symmetrical about the mode
- 4It assumes the project is progressing as scheduled
Correct answer
It is a unimodal distribution bounded by optimistic and pessimistic estimates, flexible enough to model time uncertainties
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Network Analysis PERT and CPM?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Network Analysis PERT and CPM