Computer · Construction Management
In the PERT technique, the expected time E(T) for an activity is calculated using which formula (where O = optimistic time, M = most likely time, P = pessimistic time)?
- 1E(T) = (O + 6M + P) / 6
- 2E(T) = (4O + M + P) / 6
- 3E(T) = (O + M + 4P) / 6
- 4E(T) = (O + 4M + P) / 6✓
Correct answer
E(T) = (O + 4M + P) / 6