In the PERT (Programme Evaluation and Review Technique) method, the expected time for a project activity is calculated using the formula where O is the optimistic time, M is the most likely time, and P is the pessimistic time:
- 1E(T) = O + 6M + P6
- 2E(T) = O + 4M + P6✓
- 3E(T) = 4O + M + P6
- 4E(T) = O + M + 4P6
Correct answer
E(T) = O + 4M + P6