Computer · Prestressed Concrete Structures
In the load balancing method for designing a prestressed concrete beam, the prestressing force is assumed to:
- 1Create an upward camber that balances the downward gravity loads✓
- 2Increase the moments acting on the beam
- 3Eliminate all external loading
- 4Only balance the live load on the beam
Correct answer
Create an upward camber that balances the downward gravity loads