Computer · Construction Planning and Management
In the Critical Path Method (CPM) of construction planning, which of the following statements regarding 'free float' are correct? 1. It can be greater than total float. 2. It can be greater than independent float. 3. It can be equal to total float. 4. It can be less than independent float.
- 1Only 1 and 2
- 2Only 2 and 4
- 3Only 2 and 3✓
- 4Only 1 and 4
Correct answer
Only 2 and 3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management