In the context of project evaluation, the Net Present Value (NPV) method mainly depends upon which of the following?
- 1Both income and sales-tax rates prevalent at a given time.
- 2Sales tax rate prevalent at a given time.
- 3Exchange rate prevalent at a given time.
- 4Interest rate (discount rate) prevalent at a given time.✓
Correct answer
Interest rate (discount rate) prevalent at a given time.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Evaluation and Capital Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Project Evaluation and Capital Budgeting