In the case of a well foundation, grip length is defined as the:
- 1Depth of the bottom of the well below the minimum scour level
- 2Depth of the bottom of the well below the maximum scour level✓
- 3Length between the bottom of the well cap to the cutting edge
- 4Length below the top of the well cap to the cutting edge
Correct answer
Depth of the bottom of the well below the maximum scour level