Environment & Ecology · Environmental Impact Assessment (EIA)
In the Battelle Environmental Evaluation System (EES), the total environmental impact of a project is quantitatively measured as the difference between which of the following scores?
- 1The total EIU score 'with project' and the total EIU score 'without project'✓
- 2The weighted average of pollution and human interest scores
- 3The individual quality indices of ecology and aesthetics
- 4The PIU score and the total EIU score
Correct answer
The total EIU score 'with project' and the total EIU score 'without project'
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Environment & Ecology?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Environmental Impact Assessment (EIA)?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Environment & Ecology · Environmental Impact Assessment (EIA)