In the Bar Chart (Gantt Chart) method of project management, the activities are plotted along:
- 1the ordinate (Y-axis)✓
- 2the abscissa (X-axis)
- 3both the ordinate and abscissa
- 4none of these
Correct answer
the ordinate (Y-axis)