In standard engineering drawings per BIS guidelines, a symbol representing a circular hole with a cross and a leader line specifies a hole that is to be:
- 1Drilled in the factory during initial manufacture
- 2Tapped with internal threads
- 3Drilled and fitted on site during installation✓
- 4Produced by drop forging
Correct answer
Drilled and fitted on site during installation