In project scheduling techniques like CPM/PERT, negative slack or negative float typically occurs when:
- 1Events strictly adhere to their schedule
- 2Dummy activities are large in number
- 3Activities lie on the critical path with zero float
- 4There is a deficiency of resources or time to meet the deadline✓
Correct answer
There is a deficiency of resources or time to meet the deadline