In project planning and management, a traditional Gantt bar chart depicts the project activities as:
- 1Vertical bars plotted against a vertical time scale
- 2Horizontal bars plotted against a horizontal time scale✓
- 3Vertical bars plotted against a horizontal time scale
- 4Horizontal bars plotted against a vertical time scale
Correct answer
Horizontal bars plotted against a horizontal time scale