Computer · Construction Management
In project management using PERT, the expected time (te) of an activity is calculated from optimistic time (to), most likely time (tm), and pessimistic time (tp) using which formula?
- 1(to + tm + tp) / 6
- 2(to + 4tm + tp) / 2
- 3(to + 3tm + tp) / 6
- 4(to + 4tm + tp) / 6✓
Correct answer
(to + 4tm + tp) / 6