In project management (PERT), the optimistic time estimate represents the:
- 1Average of the shortest and longest possible times
- 2Maximum time that an activity would take to complete under highly adverse conditions
- 3Time in which the activity is normally expected to complete under normal contingencies
- 4Shortest possible time in which an activity can be completed if everything goes exceptionally well✓
Correct answer
Shortest possible time in which an activity can be completed if everything goes exceptionally well
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management