Computer · Construction Management
In project management (PERT), the maximum time that an activity would take to complete under extremely adverse or difficult conditions is called:
- 1Expected time
- 2Pessimistic time✓
- 3Most likely time
- 4Optimistic time
Correct answer
Pessimistic time