Computer · Construction Planning and Management
In project management (PERT), the maximum time that an activity would take to complete if everything goes wrong or faces difficulties is called:
- 1Optimistic time
- 2Most likely time
- 3Pessimistic time✓
- 4None of the given options
Correct answer
Pessimistic time
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management