Computer · Construction Planning and Management
In project management networks, the critical path is defined as the path that gives:
- 1The path with maximum total float
- 2The average time of completion of the project
- 3The smallest time of completion of the project
- 4The longest time of completion of the project✓
Correct answer
The longest time of completion of the project