In project management networks (PERT), the time required to complete an activity under abnormal or extremely adverse conditions, excluding unpredictable acts of God, is called:
- 1Optimistic time
- 2Most likely time
- 3Pessimistic time✓
- 4Expected time
Correct answer
Pessimistic time