Computer · Construction Management
In project management networks (like CPM/PERT), 'Lag' is defined as the minimum period of time that must pass:
- 1after the start of a predecessor activity before its own completion
- 2before the end of a predecessor activity
- 3before the start of a predecessor activity
- 4after the end of a predecessor activity before the successor activity can begin✓
Correct answer
after the end of a predecessor activity before the successor activity can begin
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management