In project management networks (CPM/PERT), if: A = Earliest start time B = Latest start time C = Earliest finish time D = Latest finish time E = Total float Which of the following relations is correct?
- 1E = D + C
- 2E = B + A
- 3E2 = B2 - A2
- 4E = B - A✓
Correct answer
E = B - A