Computer · Construction Management (PERT/CPM)
In project management network techniques (PERT/CPM), the critical path represents the:
- 1shortest path for the earliest completion of the project
- 2longest path of the network from initial to final event✓
- 3path with maximum float or slack
- 4path which takes into account only parallel activities
Correct answer
longest path of the network from initial to final event