In project management network analysis (PERT), the shortest possible time in which an activity can be completed under ideal conditions is called the:
- 1Most likely time estimate
- 2Expected time estimate
- 3Pessimistic time estimate
- 4Optimistic time estimate✓
Correct answer
Optimistic time estimate