In project management, how is the cost slope defined?
- 1Crash Cost − Normal CostNormal Time
- 2Crash Cost − Normal CostCrash Time
- 3Crash CostNormal Time − Crash Time
- 4Crash Cost − Normal CostNormal Time − Crash Time✓
Correct answer
Crash Cost − Normal CostNormal Time − Crash Time