In project management (CPM/PERT), the critical path is best defined as the sequence of stages determining the:
- 1path with the highest direct resource expenditure
- 2path involving the minimum number of activities
- 3longest path through the network diagram which determines the shortest possible project duration✓
- 4shortest path with maximum float
Correct answer
longest path through the network diagram which determines the shortest possible project duration
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering