Electrical Engineering · Estimating and Costing
In project cost estimation, what do 'contingencies' typically include?
- 1Procuring specific tools and plants required for the site installation
- 2Charges for lighting, heating, and depreciation of office furniture
- 3General office expenses, administrative costs, and office rent
- 4Unexpected expenditure due to an increase in the cost rate of material or unforeseen losses✓
Correct answer
Unexpected expenditure due to an increase in the cost rate of material or unforeseen losses
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Electrical Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimating and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Electrical Engineering · Estimating and Costing